Construction Progress Update
Construction Progress Update
For Immediate Release Wednesday, July 28, 2010
Pearl Street Reconstruction Project - This project includes reconstructing Pearl Street from 4th Street to 7th Street. The reconstruction along Pearl Street includes replacing the sanitary sewer services, water main services, storm sewer intakes/pipe, paving and sidewalks. Work also includes abandoning the existing old 8 inch water main and connecting services to the newer existing 24 inch water main. Areaways under sidewalks also are to be backfilled and abandoned. New traffic signals will be installed at 5th and 6th Street intersections. The completion date is Fall of 2011. The contractor started removal on Monday, July 26th.
Sunnybrook Drive Extension - This project includes grading and paving approximately 1,580 lineal feet of roadway to connect Sunnybrook Drive to Christy Road. This project will also include construction of a regional detention pond. This street connection will provide a continuous loop between Sunnybrook Drive and Sergeant Road, provide an additional outlet for the area and allow for economic infill. The contractor is currently installing various sizes of storm sewer.
Bluff Street Bridge – This project includes construction of a new bridge over Perry Creek and modification of the road alignment to connect future Wesley Parkway to 11th Street. The contractor is forming the bridge deck. This project is 70% complete. The south pedestrian and bike Perry Creek Trail detour will be closed during working hours and open in the evenings and weekends.
Heights Neighborhood Reconstruction: Stage 3 – The contractor plans to regrade subgrade and complete C-stone subbase this week on W. 24th Street. They expect to pave mainline toward end of the week.
Heights Neighborhood Reconstruction: Stage 4 – The contractor completed mainline storm sewer on W. Solway. They are continuing with sanitary sewer main on W. Solway and water main on 24th Street.
Cunningham Drive Reconstruction – The contractor has completed removals on this full reconstruction project located south of Home Depot and is currently installing sanitary sewer main. The contractor has completed the sanitary sewer work and is installing storm sewer.
2010 Paving Patch phase I - This project includes the paving patch of 1150 square yards of concrete streets on Cheyenne Boulevard from Outer Drive to 46th Street. These street pavement sections are severely cracked and undermined with potential for cave-in. The project also includes rebuilding corners with Americans with Disabilities Act of 1990 (ADA) compliant curb ramps. Approximately 67% of this project is complete.
W. 3rd & Rebecca Street - This project includes emergency storm sewer repairs as well as repaving of the street and sidewalks due to a water main break. The closure includes Rebecca Street, beginning mid-block between W. 2nd and W. 3rd Street, and the closure of W. 3rd Street beginning mid-block between George and Rebecca and ending mid-block between Rebecca and Isabella. Pavement removal began Tuesday, July 27th. Anticipated completion date is August 9, 2010.
The Engineering Division understands that residents and businesses may be inconvenienced by the street closures and construction activities associated with these projects. We appreciate your patience and cooperation and will continue to keep you informed. You can find more information, including maps and progress updates, at our website: www.SiouxCityStreets.org. To ensure the safety of all, please be especially cautious in construction zones and along detour routes.
|
|
 |
|